成人男同av,在线黄色网,在线观看一区二区三区四区,日本六九视频,国产一区二区三区久久久久久久久,成人97视频,国产性猛交乱

軟題庫 移動APP 掃碼下載APP 隨時隨地移動學(xué)習(xí) 培訓(xùn)課程
試卷名稱 2017年信息系統(tǒng)項(xiàng)目管理師最新英語模擬題(7)
考試中心《2017年信息系統(tǒng)項(xiàng)目管理師最新英語模擬題(7)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

A company adopted globalization as a risk-mitigation strategy to deal with shrinking growth prospects in developed economies. During the risk review board meeting, the project manager realizes that the company’s global revenues are not growing at the expected rate. Where is the project manager in the project’s life cycle?
A、Risk planning phase
B、Execution of risk response
C、Control risks phase
D、Process of closing risk register


相關(guān)試題

推薦文章
合作網(wǎng)站內(nèi)容