第71題: can be described by the following characteristics:volume,variety,velocity,veracity and value. A.Artificial intelligence B.Integrated circuit C.Parallel computing D.Big data
第72題: In (),the project scope,time,and cost are determined in the early phases of the life cycle.Any changes to the scope are carefully managed. A.predictive life cycle B.iterative life cycle C.incremental life cycle D.a(chǎn)daptive life cycle 答案解析與討論:www.conferencecallsmadeeasy.com/st/5368223886.html
第73題: Project () includes making choices about resource allocation balancing competing demands examining any alternative approaches tailoring the processes to meet the project objectives and managing the inter dependencies among the Project Management Knowledge Areas. A.schedule management B.scope management C.integration management D.resource management 答案解析與討論:www.conferencecallsmadeeasy.com/st/5368311042.html