During project executing, one of the electrical engineers informs the project manager that the life cycle cost of the new heating and air conditioning system is higher than the life cycle cost of another heating and air condition system. What should the project manager do?
A、Determine if there is room in the project budget for the additional cost.
B、Select the product with the lower life cycle cost.
C、Select the product with the best life cycle cost to earned value ratio.
D、Select the product with the lowest maintenance cost to life cycle cost ratio.
10年專注信管,信管教育專注者,信管網(wǎng)優(yōu)勢(shì)
免費(fèi)試聽(tīng)信管網(wǎng)信息系統(tǒng)項(xiàng)目管理師課程
全國(guó)前50名高分學(xué)員訪談:董麗(174)、李思...
信息系統(tǒng)項(xiàng)目管理師高端班培訓(xùn)課程
信管老師100小時(shí)直播課程
軟考報(bào)名專題(報(bào)名時(shí)間、入口等)
中級(jí)系統(tǒng)集成項(xiàng)目管理工程師通關(guān)課程
系統(tǒng)規(guī)劃與管理師課程(考試介紹與題型分析)
軟題庫(kù):軟考在線題庫(kù)、支持手機(jī)答題