A stakeholder is requesting a major change to the project scope. The change is of vital repentances to the stakeholder. The project manager performs the necessary analysis of the change and finds that, because of the impact on project cost and schedule. It needs to be approved by the change control board (CCB). The CCB denies the change.What should the project manager do next?
A、Implement the change despite the decision made by the CCB, because the change is vital to the stakeholder and to the success of the project
B、Include the decision from the CCB in the change lag; notify the stakeholders and the project team of the situation
C、Recommend that the project be stopped and new requirements gathering should be performed
D、Meet with the CCB members individually to influence them to change their decision
10年專(zhuān)注信管,信管教育專(zhuān)注者,信管網(wǎng)優(yōu)勢(shì)
免費(fèi)試聽(tīng)信管網(wǎng)信息系統(tǒng)項(xiàng)目管理師課程
全國(guó)前50名高分學(xué)員訪談:董麗(174)、李思...
信息系統(tǒng)項(xiàng)目管理師高端班培訓(xùn)課程
信管老師100小時(shí)直播課程
軟考報(bào)名專(zhuān)題(報(bào)名時(shí)間、入口等)
中級(jí)系統(tǒng)集成項(xiàng)目管理工程師通關(guān)課程
系統(tǒng)規(guī)劃與管理師課程(考試介紹與題型分析)
軟題庫(kù):軟考在線題庫(kù)、支持手機(jī)答題