試卷名稱 2017年信息系統(tǒng)項目管理師最新英語模擬題(2)
考試中心《2017年信息系統(tǒng)項目管理師最新英語模擬題(2)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

A particular stakeholder has a reputation for making many changes on projects. What is the BEST approach a project manager can take at the beginning of the project to manage this situation?
A、Say "No" to the stakeholder a few times to dissuade him from submitting more changes
B、Get the stakeholder involved in the project as early as possible
C、Talk to the stakeholder's boss to find ways to direct the stakeholder's activities to another project
D、Ask that the stakeholder not be included in the stakeholder listing


相關(guān)試題

推薦文章
合作網(wǎng)站內(nèi)容