A project manager is leading the implementation of a solution that involves several emerging technologies. As a result, the project manager expects that the original project planning documents may need to be updated several times throughout the project life cycle to adjust overall project direction.What should the project manager do?
A、Develop detailed project organization charts and empower subject matter experts to approve any necessary technical scope change
B、Establish a direct and dynamic communication path with senior leadership so they are engaged in every change request
C、Inform the senior leadership that the project could not be developed once the risk of failure is identified
D、Design and implement an integrate change control system to report, control, and record changes to the original project baseline
10年專注信管,信管教育專注者,信管網(wǎng)優(yōu)勢(shì)
免費(fèi)試聽(tīng)信管網(wǎng)信息系統(tǒng)項(xiàng)目管理師課程
全國(guó)前50名高分學(xué)員訪談:董麗(174)、李思...
信息系統(tǒng)項(xiàng)目管理師高端班培訓(xùn)課程
信管老師100小時(shí)直播課程
軟考報(bào)名專題(報(bào)名時(shí)間、入口等)
中級(jí)系統(tǒng)集成項(xiàng)目管理工程師通關(guān)課程
系統(tǒng)規(guī)劃與管理師課程(考試介紹與題型分析)
軟題庫(kù):軟考在線題庫(kù)、支持手機(jī)答題