A project to create a new product line includes three new products. Product number one and two will be released together, and developed in detail immediately. Product number three will be released within two years, and developed in more detail closer to the release date. The scope management plan is completed. Which of the following describes the project’s work breakdown structure (WBS)?
A、The WBS should not include product number three, as if will not be released until a later date.
B、 The WBS template from a previous project should be used to create the WBS for this project.
C、 The WBS should be created next, and it encompasses the full scope of project work.
D、 The WBS should be created with a technique called rolling wave planning.
10年專注信管,信管教育專注者,信管網(wǎng)優(yōu)勢(shì)
免費(fèi)試聽(tīng)信管網(wǎng)信息系統(tǒng)項(xiàng)目管理師課程
全國(guó)前50名高分學(xué)員訪談:董麗(174)、李思...
信息系統(tǒng)項(xiàng)目管理師高端班培訓(xùn)課程
信管老師100小時(shí)直播課程
軟考報(bào)名專題(報(bào)名時(shí)間、入口等)
中級(jí)系統(tǒng)集成項(xiàng)目管理工程師通關(guān)課程
系統(tǒng)規(guī)劃與管理師課程(考試介紹與題型分析)
軟題庫(kù):軟考在線題庫(kù)、支持手機(jī)答題