成人男同av,在线黄色网,在线观看一区二区三区四区,日本六九视频,国产一区二区三区久久久久久久久,成人97视频,国产性猛交乱

軟題庫 移動APP 掃碼下載APP 隨時隨地移動學習 培訓課程
試卷名稱 信息系統(tǒng)項目管理師-pmp練習題-3
考試中心《信息系統(tǒng)項目管理師-pmp練習題-3》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

A new produce development project is in its closing phrase .During production, unplanned redesigning and retesting was necessary. The project manager realizes that this happened because manufacturing engineers were not included in the planning and design process.
A、Enhance individual competence
B、Document a new lesson learned
C、Perform a quality audit
D、Update risk register


相關試題

推薦文章
合作網(wǎng)站內(nèi)容