成人男同av,在线黄色网,在线观看一区二区三区四区,日本六九视频,国产一区二区三区久久久久久久久,成人97视频,国产性猛交乱

軟題庫 移動APP 掃碼下載APP 隨時隨地移動學(xué)習(xí) 培訓(xùn)課程
試卷名稱 信息系統(tǒng)項目管理師-pmp練習(xí)題-2
考試中心《信息系統(tǒng)項目管理師-pmp練習(xí)題-2》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

At the end of the project, the project manager seeks formal approval of the project closure from the sponsor. Before approving it, the sponsor requests a lessons learned workshop. This was not included in the budget and the team is confused regarding this request. What should the project manager do ?
A、Submit a change request according to the change management plan.
B、Ask the sponsor to provide funds for the lessons learned workshop.
C、Perform a lessons learned workshop since the sponsor requested it.
D、Ask the steering committee’s approval to fund the lessons learned workshop.


相關(guān)試題

推薦文章
合作網(wǎng)站內(nèi)容