The objective of a project is to improve quality of automotive components. It shows that the prototypes are often out of specification. An analysis identified multiple reasons for the variations. How does the project team determine which cause to address first ?
A、Fishbone diagram.
B、 Control chart.
C、 Pareto diagram.
D、 Run chart.