A project manager for a bidding project receives preliminary information from the client in project early stage. The client
requests a fixed-price contract for the entire project. What should the project manager do
A. Estimate the project based on similar project, explain the assumptions, and present a change management plan to the client to
protect the estimate from future scope changes.
B. Estimate the project based on similar protects, and add a reasonable amount of risk contingency to protect the estimate from future
scope changes.
C. Estimate the clearly defined requirements, and present this as a fixed-price compacts to the first part of the project.
D. Estimate the project based on the information available, and initiate claims immediately as soon as any scope changes appear.
10年專(zhuān)注信管,信管教育專(zhuān)注者,信管網(wǎng)優(yōu)勢(shì)
免費(fèi)試聽(tīng)信管網(wǎng)信息系統(tǒng)項(xiàng)目管理師課程
全國(guó)前50名高分學(xué)員訪談:董麗(174)、李思...
信息系統(tǒng)項(xiàng)目管理師高端班培訓(xùn)課程
信管老師100小時(shí)直播課程
軟考報(bào)名專(zhuān)題(報(bào)名時(shí)間、入口等)
中級(jí)系統(tǒng)集成項(xiàng)目管理工程師通關(guān)課程
系統(tǒng)規(guī)劃與管理師課程(考試介紹與題型分析)
軟題庫(kù):軟考在線題庫(kù)、支持手機(jī)答題